ROAD CLOSURES/DETOURS
CURRENT ROAD CLOSURES:
E. Boiling Spring Rd. is closed at North Lake Dam and Pine Lake Dam.
Sunset Rd. is closed at washout.
From NCDOT: Bridge Construction & Culvert Replacements on NC 133
*This information is from NCDOT. The City is not responsible for the accuracy of this information. For the most up-to-date information, please contact NCDOT, or visit DriveNC.gov.
The North Carolina Department of Transportation will be replacing existing culverts carrying Sand Hill Creek under NC 133 (River Road) with a new bridge. The project may begin as early as December 2, 2024, and is expected to be completed by Fall 2025. NC 133 (River Road) and Funston Road will be closed to through traffic during construction.
Approximately 1/2 mile of NC 133 (River Road) will be closed from North of Funston Road to South of Funston Road. Funston Road will be closed at the intersection of NC 133 (River Road). Through traffic from the South should follow NC 87 to US 17 to NC 133 at Belville. Through traffic from the North should follow US 17 to NC 87 to NC 133 North of Military Ocean Terminal at Sunny Point. Visit DriveNC.gov for a link to the detour route.
PROJECTS
Boiling Spring Lakes Dams Construction/Reconstruction Project
CONSTRUCTION HAS BEGUN!!
The City of Boiling Spring Lakes (City) is the Owner of Sanford Dam, North Lake Dam, Pine Lake Dam, and Upper Lake Dam, and is planning to solicit bids from the qualified bidders (previously vetted) for furnishing and installing all materials, labor, tools, and equipment for the construction work necessary for the construction of the Boiling Spring Lakes Dams Construction/Reconstruction Project. Please visit our Hurricane Florence page for more information on this project including a timeline. Please also visit our Dam Restoration Project FAQs for informative and helpful information.
Lakebed Vegetation Management Project (part of the dam construction/reconstruction project)
In preparation of the dam construction/reconstruction project, lakebed vegetation clearing is underway.
COMPLETED PROJECTS
Hurricane Florence EWP (Environmental Watershed Project) a/k/a Streambed Restoration Project - Construction Phase
The Project includes the following Work: debris removal, bank stabilization, stream restoration, and pond berm stabilization across eight (8) sites within the City. The City's contractor Shamrock is almost finished with the project. The updated completion date is April 30, 2023. Project cost: $2,285,180.55
New Police Department Building
The City purchased an existing 2,617 SF “Class B” one-story former bank/office building on a 1.66 acre commercial property with the intention of renovating it and adding approximately 2,000 SF – 2,500 SF to accommodate the police department. The building is located at 3020 George II Highway in Boiling Spring Lakes, North Carolina. Samet Construction is the contractor. Demolition is finished and construction is underway. Project cost: $1,900,000
Railroad Culvert Project
The City of Boiling Spring Lakes (CBSL) has experienced flooding at the intersection of Cardinal Road and Fifty Lakes Drive. Stormwater runoff was being conveyed to a 24" diameter pipe under the Military Ocean Terminal Sunny Point Railroad line at this location. The 24" diameter pipe was significantly undersized as evidence by the stormwater back up. CBSL is currently in the process of installing a 60" diameter Reinforced Concrete Pipe via dry bore and jack method under the railroad line adjacent to the existing 24” pipe. Along with the 60” pipe they will be constructing concrete endwalls and placing rip rap lining at the pipe ends. They will also be slip lining the existing 24” pipe to keep it in service along with the 60” pipe. As of this date the 60” pipe installation, construction of the endwalls and slip lining the existing 24” pipe is complete. It is anticipated that final stream grading and placement of the rip rap will be complete by 11/30/22, weather dependent. Along with the pipe work at the railroad crossing the CBSL has also installed a 24” diameter pipe and triple 36”diameter pipes under Cardinal Road and double 24” diameter pipes under Fifty Lakes Drive at this location to help with stormwater conveyance.
Drayton Road Paving
This paving project was totally funded by a grant City staff applied for and received to pave Drayton Road. Drayton Road is the road that will be used as a detour once the dam restoration project is underway. The grant received was $922,306 and the total cost of the project was $768,973. The City determined that guardrails needs installation on certain section of Drayton Road. The funds for this project will come from the remainder of the Grant funds. The City is not authorized to keep funds that were not used for the project.