Electrical Permit's
Solar Panels
- Site Plan
- Plans
- Ground Mounted – Zoning Permit
- Plus, Building Permit with Structural Letter - 150 MPH Wind
- Solar Panel Inspection Options
- Copy of Contract with Homeowner
Generator
- Site Plan
- Load Calculations
*****************************
Building Permit's
Accessory Use
- Zoning Permit
- Drawing with dimensions and building materials
- Storage Building – Wind Verification – 150 MPH
- Pools - Specification Information
New Home / Addition
- Zoning Permit
- Wastewater Authorization to Construct / Sewer Verification
- Wastewater Authorization to Construct:
- Issued by Brunswick County Environmental Health Department 910-253-2250
- or Brunswick County Sewer availability - Brunswick County Utilites 910-253-2655
- Wastewater Authorization to Construct:
- Potable Water
- Brunswick County Water Fee Receipt - Brunswick County Utilities 910-253-2655
- Well Permit:
- Issued by Brunswick County Environmental Health Department 910-253-2250
- Floor Plan with Dimensions and Room Use
- See Residential Plan Review Requirements
- Lien Agent Information – Construction Cost over $30,000.00
- Proof of Workers' Compensation Insurance or Workers' Comp Affidavit
- Truss Plans as Soon as Available
New Home Construction Notes:
Work site address must be posted and visible from the street at the footing foundation inspection.
- Must be built to 2018 Residential Building Code Requirements
- All subcontractors must get their own permit before starting work.
- Zoning Department - Foundation and Final survey's are required
- Silt fence must be up and temporary toilets must be screened
- Schedule your final site zoning and final driveway inspections when ready through online inspection request form
- Construction debris must be contained
Additional Information before Certificate of Occupancy – New Home / Addition
- Zoning Compliance Certificate
- Wastewater Operational Permit – Issued by Brunswick County Environmental Health
- Sewer Properties with Grinder - Final inspection - Contact Brunswick County Utilities 910-253-2860
Sec- 9.90 Certain noises expressly prohibited.
(8) The erection, construction (including excavation), demolition, alteration or repair of any building or structure in a residential or business district other than between the hours of 7:00 AM to 8:00 PM
Sec. 4-26. General requirements for new construction projects.
All new construction projects located within the jurisdiction for the city shall comply with the following:
(1) Temporary toilet facilities. All temporary toilet facilities shall be located on the property they serve and not on public street rights-of-way. The facility will be installed on the property as follow:
a. With the door facing away from the public street or if a corner lot, at a forty-five (45) degree angle;
b. Away from the construction access point: and
c. Enclosed on three (3) sides by lattice secured to twelve (12) foot 4 × 4 post installed a minimum of three (3) feet in the ground. (Res. No. 2008-08, § 2, 3-4-08)